Burr Street DOT Project

IMG_20180824_082357
IMG_20180615_160942
IMG_20180822_114046

Phase 1 (Northbound Lanes)  Concrete Pavement - Near Completion 

Phase 2 (Southbound Lanes) Under  Construction

Single lane, two-way traffic is in the current southbound lanes from I90 to Spruce Street.  Traffic is moved to the new northbound lanes south of Spruce Street.

Phase 1 is the reconstruction of the northbound lanes and East Spruce Street.  Phase 2 is the reconstruction of the southbound lanes and West Spruce Street.

Process: 

1. Water Main

2. Storm Sewer

3. Excavation and stabilization of grade.

4. Gravel Cushion

5. Mainline Concrete Pavement.

6.  Curb and Gutter

7. Concrete Entrances and radii

8. Sidewalk

9. Topsoil Placement

10. Seeding

Water main installation is complete except the road crossing at Highland Way and the road crossing on Burr Street.

Grading is complete from Spruce Street south to the beginning of the project approximately 1/2 mile south of Spruce Street.  Grading will continue from Spruce Street north and concrete pavement will follow.