Burr Street DOT Project

IMG_20180501_114309
IMG_20180604_083857
IMG_20180703_111648

 Phase 1 (Northbound Lanes) Under Construction

Single lane, two-way traffic is in the current southbound lanes from I90 to Spruce Street.

Phase 1 involve reconstruction of the northbound lanes and East Spruce Street. 

Process: 

1. Water Main

2. Storm Sewer

3. Excavation and stabilization of grade.

4. Gravel Cushion

5. Mainline Concrete Pavement.

6.  Curb and Gutter

7. Concrete Entrances and radii

8. Sidewalk

9. Topsoil Placement

10. Seeding

Water main installation is complete except the road crossing at Highland Way and the road crossing on Burr Street.

Grading is complete from Spruce Street south to the beginning of the project approximately 1/2 mile south of Spruce Street.  Grading will continue from Spruce Street north and concrete pavement will follow.